CHP cascades: when several units replace a single large one
Updated: 4 days ago
A site with a base load above 630 kW — the rated output of the largest standard model, the DvGA-630 — can be covered in two ways: with a single higher-output unit or with a cascade of several. The choice is driven not only by kilowatts but by the load profile, the requirement for uninterrupted generation and the plant’s development plans. Below: when a cascade is justified, how it works and what changes in the project compared with a single unit.

1. What aggregation means
Aggregation is the combination of several cogeneration units at one site, working onto a common electrical busbar and a common thermal circuit. The units are synchronised with each other and with the grid, and the load is distributed between them by the control system.
A cascade of two DvGA-500 units delivers 1 MW of electrical output, two DvGA-630 units — 1.26 MW. Total thermal output adds up the same way: about 1,440 kW and about 1,800 kW respectively. The number of units in a cascade is limited by the capacity of the gas pipeline, the rating of the grid connection and the available footprint.
2. When a cascade is justified
■ Base load above a single model. The DvGA-630 is rated at 630 kW; above that level the choice is between the DvGA-750 and a cascade of two or more units. A single unit is simpler to service; a cascade is more flexible in regulation and does not stop generation completely during repairs.
■ Uneven load profile. Seasonal production, plants running two or three shifts, sites where summer and winter consumption differ several times over. A cascade allows as many units to run as the current load requires.
■ Requirement for continuity. Sites where a stop in generation is unacceptable: district heating, continuous process industries, sites with their own distribution network. During scheduled service or repair of one engine the remaining units of the cascade stay in operation, and the site does not lose its own generation entirely.
■ Phased plant development. The load grows according to the equipment commissioning schedule. The first unit covers current base consumption; the second and subsequent ones are added as the load actually grows.
3. How output is regulated
In a cascade the units operate in steps. One carries the base load continuously, the others are brought on and off line as consumption changes. The control system distributes the load so that the running units stay in the zone of high fuel utilisation, rather than sharing the load equally at partial output.
This is the main difference from a single unit. One 1 MW machine at 500 kW of demand runs at half output with worse specific consumption. Two 500 kW machines in the same situation give one running at rated output and one shut down.
Engine hours are consumed only by the running units. In stepped operation, running hours are distributed between the machines and scheduled repairs fall at different times instead of coinciding.
4. Uninterrupted generation during service
Service schedule: intermediate overhaul after 40,000 engine hours, major overhaul after 80,000, total service life of the 6ГЧН25/34 and 8ГЧН25/34 engines — 240,000 engine hours. A unit is shut down for the duration of a repair.
At a site with a single unit this means a full switch to the grid or to a backup source. In a cascade of two or more machines, while one is under repair the others keep running: the site retains part of its generation and all the heat output that goes with it. For district heating utilities and continuous production this is the main argument in favour of a cascade.
Scheduled service in this case is carried out unit by unit, during the period of minimum load. This approach is used, among others, at district heating sites: routine work is done in summer, when the thermal load is at its lowest.
5. What changes in the project
■ Electrical part. Synchronisation of the units with each other and with the grid is required, together with a common busbar and a load-sharing and protection system. The control cabinet is designed for the number of machines in the cascade.
■ Thermal circuit. The recovery heat exchangers work onto a common header. The scheme is calculated for the total thermal output, allowing for some units being shut down.
■ Gas supply. The capacity of the gas pipeline is checked against total consumption. Rated gas consumption is 133 Nm³/h for the DvGA-500 and 167 Nm³/h for the DvGA-630; a cascade of two DvGA-500 units requires about 266 Nm³/h when both run simultaneously.
■ Footprint. A containerised DvGA-500 module occupies about 25–30 m², a DvGA-630 — 30–35 m². The area for a cascade is calculated per unit, allowing for service access and vehicle access for removing components during repairs.
The footprint, the gas inlet and the electrical part are designed for the full number of units from the outset, even if the second and subsequent ones are installed later. Reworking the infrastructure after the first machine has been commissioned costs more than designing with reserve at the feasibility study stage.
6. Economics of a cascade
The cost per kilowatt of installed capacity is higher in a cascade than in a single machine of the same total output: the frame, exhaust system, heat exchangers and part of the control equipment are duplicated. This difference is built into the project CAPEX.
It is recovered in operation. A cascade maintains high fuel utilisation under variable load and does not lose output during scheduled repairs. At a site with an uneven profile and a continuity requirement, these two factors produce a gain over the service life that a single unit cannot deliver.
The balance is calculated case by case: with a steady load that fits within the range of a single model, a cascade loses — a single unit is the right answer there. The calculation for a specific consumption profile is made in the feasibility study.
Reference figures from the feasibility study of 01.07.2026 for a single DvGA-500: 8,000 h/year, gas UAH 30/Nm³, electricity UAH 12/kWh, turnkey project cost UAH 20 million, annual economic effect UAH 11.7 million, payback period 1.7 years. For a cascade the calculation is made separately, against the site’s actual load profile.
7. When a cascade is not needed
■ the base load fits within the range of a single model and stays steady through the year;
■ stopping generation for a scheduled repair is acceptable — the site switches to the grid without harm to the process;
■ the site area or the gas pipeline capacity do not allow a second and subsequent units to be installed and supplied;
■ load growth is not confirmed by an equipment commissioning schedule and remains hypothetical.
In these cases a single unit of the appropriate output gives lower CAPEX and simpler operation.
8. Input data for sizing a cascade
■ electrical load profile for the past 12 months, preferably hourly, broken down by season;
■ minimum, average and maximum consumption during working hours;
■ continuity requirement: whether a stop in generation is acceptable and for how long;
■ thermal load profile and the presence of a heat consumer for the cascade’s total output;
■ technical conditions: gas pipeline capacity, gas pressure, rating of the grid connection;
■ commissioning schedule for new equipment, if load growth is planned;
■ available area and access for servicing.
The sizing procedure based on the load profile is set out in the article “CHP power sizing”. Model specifications are given in the article “DvGA-500 and DvGA-630: technical specifications”.
Timescales
The full project cycle to industrial start-up is 2–6 months: design 2–6 weeks, manufacturing 1–10 weeks, installation 1–2 weeks, commissioning 1–3 weeks. Many stages run in parallel: site preparation, obtaining technical conditions and external network work proceed alongside manufacturing, so the total time to start-up is set by the schedule of overlapping activities rather than by simply adding the stages together. For a cascade, design is done once for the whole complex, while installation and commissioning of the units proceed sequentially or in parallel, depending on the commissioning schedule.
A feasibility study with a payback calculation is prepared within 3–5 working days, a commercial proposal within 2. The standard warranty on the units is 1–2 years.
Send us your consumption profile for the past 12 months, your continuity requirements and the technical conditions for connection. Our engineers will determine the scheme — a single unit or a cascade — and prepare a feasibility study.